Case facts
Modification to Reg.Ref.3215/16 to consist of increase of site boundary to include 6 Rathgar Road, fire escape corridor, omit entrance doors, roof lights, works to shopfront and facade.
- Planning authority
- Dublin City Council
- Council reference
- 2623/17
- Council decision
- —
- Commission decision
- Other 20 Oct 2017unmapped
- Inspector's recommendation
- Board Direction PL29S 248772 The submissions on this file and the Inspector's report were considered at a Board meeting held on 10th October…decided to grant permission generally in accordance with the Inspector's recommendation, for the following reasons and considerations, and subject to the following conditions
Timeline
- 26 Jun 2017Appeal received by ACP
- 20 Oct 2017Appeal decidedJr window closed 15 Dec 2017
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Matched passages full-text search
- Board Direction PL29S 248772 The submissions on this file and the Inspector's report were considered at a Board meeting held on 10th October…decided to grant permission generally in accordance with the Inspector's recommendation, for the following reasons and considerations, and subject to the following conditions
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 23:29 | open |