8 weeks from the Commission's decision (25 Jul 2018) · s.50 Planning and Development Act 2000
Case facts
10 year permission for development. Underground electricity cabling from Lenalea windfarm to substation in Cark. 110kV cabling from substation in Cark to Clogher Substation, Cullionboy,
- Planning authority
- Donegal County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Refused 25 Jul 2018
- Inspector's recommendation
- No inspector's report published.
Timeline
- 29 Jun 2017Appeal received by ACP
- 25 Jul 2018Appeal decidedJr window closed 19 Sept 2018
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 18 Sept 2026, 16:04
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 18 Sept 2026, 16:04 | open |