An Coimisiún Pleanála · PL29S.248958 · Planning Appeal
Industries Factory, Chapelizod Hill Road, Chapelizod, Dublin 20.
Received by the Commission 31 Jul 2017We first saw it 11 Sept 2026, 23:29
Judicial review window closes 8 Feb 2018 closed 3154 days ago
8 weeks from the Commission's decision (5 Dec 2017) · s.50 Planning and Development Act 2000
Case facts
Demolition of factory and two dwellings, Construction of 171 no. apartments, creche, car park with ESB substation, fire tender access, railing boundary and site development works. Faulkner
- Planning authority
- Dublin City Council
- Council reference
- 2869/17
- Council decision
- —
- Commission decision
- Granted with conditions 5 Dec 2017
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 31 Jul 2017Appeal received by ACP
- 5 Dec 2017Appeal decidedJr window closed 8 Feb 2018
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |