An Coimisiún Pleanála · 302263 · Appeal
Kilnamucky Tower, Co. Cork
Residential development of 58 dwelling houses: appeal withdrawn 8 Nov 2018.
Received by the Commission 7 Aug 2018We first saw it 18 Sept 2026, 16:04
Judicial review window closes 14 Jan 2019 closed 2837 days ago
8 weeks from the Commission's decision (8 Nov 2018) · s.50 Planning and Development Act 2000
Case facts
Construct a residential development of 58 no. dwelling houses and all ancillary site development works
- Planning authority
- Cork County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Withdrawn 8 Nov 2018
- Inspector's recommendation
- No inspector's report published.
Timeline
- 7 Aug 2018Appeal received by ACP
- 8 Nov 2018Appeal decidedJr window closed 14 Jan 2019
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 18 Sept 2026, 16:04 | open |