Case facts

10 year permission for an up to 100MW Battery Energy Storage Facility providing energy services to the National Grid consisting of construction and operation of up to 34 metal containers.

Planning authority
Carlow County Council
Council reference
Council decision
Commission decision
Granted with conditions 23 Sept 2019
Inspector's recommendation
No inspector's report published.

Timeline

  • 25 Feb 2019
    Appeal received by ACP
  • 23 Sept 2019
    Appeal decided
    Jr window closed 18 Nov 2019

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: acp · fetched 18 Sept 2026, 16:04
    SourceLicenceFetchedLink
    acpCC-BY-4.018 Sept 2026, 16:04open