An Coimisiún Pleanála · TA06S.305763 · Strategic Housing Development - Application
Strategic Housing Development ABP-305763-19 · Commission category: Housing
Site at the corner of Airton Road and Belgard Road, Tallaght, Dublin 24. (www.airtonplazashd.ie)
Received by the Commission 25 Oct 2019We first saw it 11 Sept 2026, 23:29
Judicial review window closes 16 Apr 2020 closed 2358 days ago
8 weeks from the Commission's decision (20 Feb 2020) · s.50 Planning and Development Act 2000
This case is Airton Road and Belgard Road Site — 328 homes, by Power Scaffolding Supplies Limited. Read the scheme page →
Building progress as the Dublin councils report it, Q1 2025
All 328 permitted homes are built (Q1 2025).
328
homes permitted
328
homes started on site
328
homes completed
completed · under construction · not started · 0 houses and 328 apartments permitted
Case facts
Demolition of existing buildings, construction of 328 no. apartments, creche and associated site works.
- Planning authority
- South Dublin County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 20 Feb 2020
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 25 Oct 2019Appeal received by ACP
- 20 Feb 2020Appeal decidedJr window closed 16 Apr 2020
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |