An Coimisiún Pleanála · PL29S.305797 · Planning Appeal
Site known as 2b Chapelizod Village, (rear 2 Mullingar Terrace), Chapelizod, Dublin 20
House: granted on appeal 23 Dec 2019.
Received by the Commission 29 Oct 2019We first saw it 11 Sept 2026, 23:29
Judicial review window closes 26 Feb 2020 closed 2425 days ago
8 weeks from the Commission's decision (23 Dec 2019) · s.50 Planning and Development Act 2000
Case facts
Construction of a house
- Planning authority
- Dublin City Council
- Council reference
- WEB1122/19
- Council decision
- Refuse permission 1 Oct 2019
- Commission decision
- Granted with conditions 23 Dec 2019
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 5 Mar 2019Application received by the council
- 1 Oct 2019Council decision — Refuse permission
- 29 Oct 2019Appeal received by ACP
- 23 Dec 2019Appeal decidedJr window closed 26 Feb 2020
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 23:29 | open |