An Coimisiún Pleanála · PL06F.306429 · Planning Appeal
14 Chapel Street, Balbriggan, Co Dublin, K32 V086
Pre-fabricated dwelling retention: refused on appeal 26 Mar 2020.
Received by the Commission 16 Jan 2020We first saw it 11 Sept 2026, 15:23
Judicial review window closes 21 May 2020 closed 2341 days ago
8 weeks from the Commission's decision (26 Mar 2020) · s.50 Planning and Development Act 2000
Case facts
Retention of pre-fabricated dwelling & garden, future erection of porch and future internal modifications to house
- Planning authority
- Fingal County Council
- Council reference
- F19A/0507
- Council decision
- Refuse permission & refuse retention 11 Dec 2019
- Commission decision
- Refused 26 Mar 2020
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 29 Oct 2019Application received by the council
- 11 Dec 2019Council decision — Refuse permission & refuse retention
- 16 Jan 2020Appeal received by ACP
- 26 Mar 2020Appeal decidedJr window closed 21 May 2020
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 15:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 15:23 | open |