PlanningRegister.ie
An Coimisiún Pleanála · PL29N.307346 · Planning Appeal

49, Elm Mount Rise, Dublin 9

Received by the Commission 17 Jun 2020We first saw it 11 Sept 2026, 23:29
Judicial review window closes 12 Nov 2020 closed 2139 days ago
8 weeks from the Commission's decision (17 Sept 2020) · s.50 Planning and Development Act 2000

Case facts

Proposed dormer roof to the rear of the house roof and a proposed new gable wall to the side of the house.

Planning authority
Dublin City Council
Council reference
2348/20
Council decision
Grant permission 11 Jun 2020
Commission decision
Granted with conditions 17 Sept 2020
Inspector's recommendation
See the inspector's report (not yet indexed).

Timeline

  • 26 Feb 2020
    Application received by the council
  • 11 Jun 2020
    Council decisionGrant permission
  • 17 Jun 2020
    Appeal received by ACP
  • 17 Sept 2020
    Appeal decided
    Jr window closed 12 Nov 2020

Documents

Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

Provenance

Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

Source: acp · fetched 11 Sept 2026, 23:29
SourceLicenceFetchedLink
acpCC-BY-4.011 Sept 2026, 23:29open