PlanningRegister.ie
An Coimisiún Pleanála · RL29S.310281 · Referral

Lamplighters Pub, 79 The Coombe / 1 Brabazon Street, Dublin 8

Exemption: referral decided 22 Sept 2021.

Received by the Commission 11 May 2021We first saw it 11 Sept 2026, 23:29
Judicial review window closes 17 Nov 2021 closed 1801 days ago
8 weeks from the Commission's decision (22 Sept 2021) · s.50 Planning and Development Act 2000

Case facts

Whether the internal alteration of a 5 bedrooms accommodation for a maximum of 11 guests to a 9 bedrooms accommodation for a maximum of 18 guests is or is not development or is or is not exempted development and whether the change of use from short term lettings in excess of 15 days duration per letting to a short term letting for any period not exceeding 14 days, is or is not development and if development, whether it is exempted development or not.

Planning authority
Dublin City Council
Council reference
0103/21
Council decision
—
Commission decision
Split 22 Sept 2021
Inspector's recommendation
See the inspector's report (not yet indexed).

Timeline

  • 11 May 2021
    Appeal received by ACP
  • 22 Sept 2021
    Appeal decided
    Jr window closed 17 Nov 2021

Documents

Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

Provenance

Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
SourceLicenceFetchedLink
An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.011 Sept 2026, 23:29open