An Coimisiún Pleanála · PL06D.310899 · Planning Appeal
No. 3 St. Lukes Crescent, Milltown, Dublin 14
First floor extension to the side: planning appeal lodged 21 Jul 2021.
Received by the Commission 21 Jul 2021We first saw it 11 Sept 2026, 15:23Decision due 23 Nov 2021
Appeal pending
No decision yet; the judicial-review window (8 weeks, s.50 PDA 2000) opens when the Commission decides.
Case facts
Construction of a first floor extension to the side of the existing dwelling including alterations to the exist single storey side extension, first floor extension and single storey extension to the rear of the existing dwelling, and all associated site works.
- Planning authority
- Dún Laoghaire-Rathdown County Council
- Council reference
- D21A/0371
- Council decision
- Refuse permission 22 Jun 2021
- Commission decision
- pending
- Inspector's recommendation
- No inspector's report published.
Timeline
- 28 Apr 2021Application received by the council
- 22 Jun 2021Council decision — Refuse permission
- 21 Jul 2021Appeal received by ACP
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 15:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 15:23 | open |