An Coimisiún Pleanála · 311565 · Appeal
Strategic Infrastructure Development ABP-311565-21 · Commission category: SID (Not incl LAP SID cases)
Ballagh, Billistown, Ballynacar and Bracklin, County Westmeath and Coolronan, County Meath
Wind Farm Development: granted on appeal 7 Jul 2022.
Received by the Commission 5 Oct 2021We first saw it 18 Sept 2026, 16:04
Judicial review window closes 1 Sept 2022 closed 1547 days ago
8 weeks from the Commission's decision (7 Jul 2022) · s.50 Planning and Development Act 2000
Case facts
Wind Farm Development including 9 turbines and all associated works
- Planning authority
- Westmeath County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 7 Jul 2022
- Inspector's recommendation
- No inspector's report published.
Timeline
- 5 Oct 2021Appeal received by ACP
- 7 Jul 2022Appeal decidedJr window closed 1 Sept 2022
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 18 Sept 2026, 16:04 | open |