An Coimisiún Pleanála · PL29S.311692 · Planning Appeal
Royal Hospital Donnybrook, Morehampton Road, Donnybrook, Dublin 4, D04 HX40
4 storey Health Care Centre: granted on appeal 22 Dec 2022.
Received by the Commission 18 Oct 2021We first saw it 11 Sept 2026, 23:29
Judicial review window closes 27 Feb 2023 closed 1328 days ago
8 weeks from the Commission's decision (22 Dec 2022) · s.50 Planning and Development Act 2000
Case facts
Construction of a 4 storey Health Care Centre
- Planning authority
- Dublin City Council
- Council reference
- 2843/21
- Council decision
- Grant permission 21 Sept 2021
- Commission decision
- Granted with conditions 22 Dec 2022
- Inspector's recommendation
- Responses...................................................................................... 56 7.0 Assessment ....................................................................................................... 56 8.0 Recommendation............................................................................................... 69 9.0 Reasons and Considerations ............................................................................. 69 10.0 Conditions ................................................................................................... 70 ABP 311692-21 Inspector’s Report Page
Timeline
- 28 May 2021Application received by the council
- 21 Sept 2021Council decision — Grant permission
- 18 Oct 2021Appeal received by ACP
- 22 Dec 2022Appeal decidedJr window closed 27 Feb 2023
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Matched passages full-text search
- Responses...................................................................................... 56 7.0 Assessment ....................................................................................................... 56 8.0 Recommendation............................................................................................... 69 9.0 Reasons and Considerations ............................................................................. 69 10.0 Conditions ................................................................................................... 70 ABP 311692-21 Inspector’s Report Page
- therefore are not for consideration under the subject appeal. I recommend, therefore, that the proposed development is not refused permission on these grounds…appeal. 1 https://www.dublinbus.ie/RTPI/Sources-of-Real-Time- Information/?searchtype=map&searchquery= ABP 311692-21 Inspector’s Report Page
- Risk Assessment • The Drainage Division are satisfied with the proposal and recommends conditions. • The Drainage Division report notes that the development is located…risk from groundwater flooding. Therefore flood risk is minimal. ABP 311692-21 Inspector’s Report Page
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 23:29 | open |