Received by the Commission 12 Jan 2022We first saw it 11 Sept 2026, 15:23
Judicial review window closes 30 Aug 2023 closed 1109 days ago
8 weeks from the Commission's decision (5 Jul 2023) · s.50 Planning and Development Act 2000
Case facts
Development consisting of: 1) demolition of the two storey extension to 'Rusheen', the habitable dwelling on the site (224 sq. m. GFA), and the ancillary single storey garage (37.4 sq.m. GFA); 2) construction of a three storey, five bedroom house (521 sq.m), with a single storey link to connect 'Rusheen' to the house, and a single storey detached double garage (36 sq.m GFA); and 3) all other site works
- Planning authority
- Dún Laoghaire-Rathdown County Council
- Council reference
- D21A/0908
- Council decision
- Refuse permission 9 Dec 2021
- Commission decision
- Granted with conditions 5 Jul 2023
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 18 Oct 2021Application received by the council
- 9 Dec 2021Council decision — Refuse permission
- 12 Jan 2022Appeal received by ACP
- 5 Jul 2023Appeal decidedJr window closed 30 Aug 2023
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 15:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 15:23 | open |