An Coimisiún Pleanála · 312659 · Appeal
Strategic Infrastructure Development ABP-312659-22 · Commission category: SID (Not incl LAP SID cases)
Glenard and other townlands, Co. Donegal
Windfarm development: granted on appeal 25 Feb 2025.
Received by the Commission 4 Feb 2022We first saw it 18 Sept 2026, 16:04
Judicial review window closes 22 Apr 2025 closed 569 days ago
8 weeks from the Commission's decision (25 Feb 2025) · s.50 Planning and Development Act 2000
Case facts
Windfarm development including 15 no. wind turbines, 1 no. 110kV electrical substation, 110kV connection line and all associated and ancillary works.
- Planning authority
- Donegal County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 25 Feb 2025
- Inspector's recommendation
- No inspector's report published.
Timeline
- 4 Feb 2022Appeal received by ACP
- 25 Feb 2025Appeal decidedJr window closed 22 Apr 2025
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04