An Coimisiún Pleanála · 313007 · Appeal
Ballynagare, Dysert Marshes, Farrandeen, Monument, Knockaunacurraheen, Ballintogher, Ballnageragh, Clooncolla, Ballyhorgan West, Ballyhorgan East, Lissahane, Knockburrane, Ballygarret, Banemore, Pallas, Co Kerry
10 Year permission: refused on appeal 19 Sept 2023.
Received by the Commission 14 Mar 2022We first saw it 18 Sept 2026, 16:04
Judicial review window closes 14 Nov 2023 closed 1069 days ago
8 weeks from the Commission's decision (19 Sept 2023) · s.50 Planning and Development Act 2000
Case facts
10 Year permission and 35 operational life for wind farm comprising; 7 wind turbines, a permanent meterological mast and all ancillary plant & equipment. The application is accompanied by a Natura Impact (Nis) and Environmental Impact Assessment Report (EIAR).
- Planning authority
- Kerry County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Refused 19 Sept 2023
- Inspector's recommendation
- No inspector's report published.
Timeline
- 14 Mar 2022Appeal received by ACP
- 19 Sept 2023Appeal decidedJr window closed 14 Nov 2023
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04