Case facts
BusConnects Ballymun/Finglas to City Centre Core Bus Corridor Scheme
- Planning authority
- Dublin City Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 12 Mar 2024
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 9 Sept 2022Appeal received by ACP
- 12 Mar 2024Appeal decidedJr window closed 7 May 2024
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |