An Coimisiún Pleanála · HA29.314610 · LA Road Dev - Application

Strategic Infrastructure Development ABP-314610-22 · Commission category: LAP SID

Ballymun/Finglas to Dublin City Centre

BusConnects Ballymun/Finglas to City Centre Core: granted on appeal 12 Mar 2024.

Received by the Commission 9 Sept 2022We first saw it 11 Sept 2026, 23:29
Judicial review window closes 7 May 2024 closed 907 days ago
8 weeks from the Commission's decision (12 Mar 2024) · s.50 Planning and Development Act 2000

Case facts

BusConnects Ballymun/Finglas to City Centre Core Bus Corridor Scheme

Planning authority
Dublin City Council
Council reference
—
Council decision
—
Commission decision
Granted with conditions 12 Mar 2024
Inspector's recommendation
See the inspector's report (not yet indexed).

Timeline

  • 9 Sept 2022
    Appeal received by ACP
  • 12 Mar 2024
    Appeal decided
    Jr window closed 7 May 2024

Documents

Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

Provenance

Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
SourceLicenceFetchedLink
An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.011 Sept 2026, 23:29open