Main Street, Broadford, Co. Clare

Exemption: referral decided 10 May 2024.

Received by the Commission 2 Dec 2022We first saw it 18 Sept 2026, 16:04
Judicial review window closes 5 Jul 2024 closed 876 days ago
8 weeks from the Commission's decision (10 May 2024) · s.50 Planning and Development Act 2000

Case facts

Whether the (i) cleaning and painting of a wall, (ii) replacement of windows, (iii) repair of roof, (iv) erection of internal walls, doors and floors, (v) replacement of stairs, (vi) erection of a boiler house and internal walls and doors, (vii) erection of path, (viii) installation of 12sq.m of solar panels is or is not development and is or is not exempted development.

Planning authority
Clare County Council
Council reference
—
Council decision
—
Commission decision
Other 10 May 2024
referral_not_exempt
Inspector's recommendation
No inspector's report published.

Timeline

  • 2 Dec 2022
    Appeal received by ACP
  • 10 May 2024
    Appeal decided
    Jr window closed 5 Jul 2024

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.018 Sept 2026, 16:04open