Case facts
Material change of use from studio workshop to residential use and all associated site works.
- Planning authority
- Dublin City Council
- Council reference
- WEB1923/22
- Council decision
- Grant permission 30 Nov 2022
- Commission decision
- Granted with conditions 23 Jan 2024
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 6 Oct 2022Application received by the council
- 30 Nov 2022Council decision — Grant permission
- 3 Jan 2023Appeal received by ACP
- 23 Jan 2024Appeal decidedJr window closed 19 Mar 2024
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |