Case facts
Protected Structure: Retention for modifications. change of use to dwelling comprising of construction of extension and all associated site works.
- Planning authority
- Dublin City Council
- Council reference
- 5170/22
- Council decision
- Grant permission and rete 13 Dec 2022
- Commission decision
- Withdrawn 7 Mar 2023
- Inspector's recommendation
- No inspector's report published.
Timeline
- 4 Nov 2022Application received by the council
- 13 Dec 2022Council decision — Grant permission and rete
- 5 Jan 2023Appeal received by ACP
- 7 Mar 2023Appeal decidedJr window closed 2 May 2023
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 23:29 | open |