PlanningRegister.ie
An Coimisiún Pleanála · 315622 · Appeal

Townlands of Ballinlough, Ballinure, Monfieldstown, and Rochestown, Co. Cork

Passage Railway Greenway Improvement Scheme: granted on appeal 21 Feb 2024.

Received by the Commission 23 Jan 2023We first saw it 18 Sept 2026, 16:04
Judicial review window closes 17 Apr 2024 closed 919 days ago
8 weeks from the Commission's decision (21 Feb 2024) · s.50 Planning and Development Act 2000

Case facts

Passage Railway Greenway Improvement Scheme, Phase II ? Mahon to Passage West, and all associated works. Phase II of the Greenway route commences on the northern side of the N40 near Bessborough, crosses the N40 Cork South Ring Road and the Douglas Estuary via bridges, traverses Harty?s Quay and the R610 Rochestown Road, passes Hop Island and terminates at the Cork City boundary to the west of Passage West. The proposed development also includes improvement works to pedestrian / cycle tracks that extend from the northern section of the Greenway towards Mahon Industrial Estate and Mahon Interchange.

Planning authority
Cork City Council
Council reference
—
Council decision
—
Commission decision
Granted with conditions 21 Feb 2024
Inspector's recommendation
No inspector's report published.

Timeline

  • 23 Jan 2023
    Appeal received by ACP
  • 21 Feb 2024
    Appeal decided
    Jr window closed 17 Apr 2024

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.018 Sept 2026, 16:04open