Planning Register
An Coimisiún Pleanála · PL06F.317806 · Planning Appeal

8 Boroimhe Blackthorn, Swords, Co. Dublin, K67 T853

Received by the Commission 15 Aug 2023We first saw it 11 Sept 2026, 15:23
Judicial review window closes 10 Oct 2023 closed 1068 days ago
8 weeks from the Commission's decision (15 Aug 2023) · s.50 Planning and Development Act 2000

Case facts

Retention: partial ground floor only extension. Permission: new flat dormer roof to existing house roof

Planning authority
Fingal County Council
Council reference
F23A/0333
Council decision
Refuse permission & grant retention 4 Aug 2023
Commission decision
Invalid 15 Aug 2023
Inspector's recommendation
No inspector's report published.

Timeline

  • 14 Jun 2023
    Application received by the council
  • 4 Aug 2023
    Council decisionRefuse permission & grant retention
  • 15 Aug 2023
    Appeal decided
    Jr window closed 10 Oct 2023
  • 15 Aug 2023
    Appeal received by ACP

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: acp · fetched 11 Sept 2026, 15:23
    SourceLicenceFetchedLink
    acpCC-BY-4.011 Sept 2026, 15:23open