An Coimisiún Pleanála · PL29N.318454 · Planning Appeal
52 & 54 Quarry Road, Cabra, Dublin 7
Received by the Commission 14 Nov 2023We first saw it 11 Sept 2026, 23:29
Applications only for this county. Appeals, zoning, RZLT and consultations: Dún Laoghaire-Rathdown and Fingal only for now.
Judicial review window closes 5 Nov 2024 closed 676 days ago
8 weeks from the Commission's decision (10 Sept 2024) · s.50 Planning and Development Act 2000
Case facts
Demolition of existing structures and construction of a mixed commercial/residential development of 64 units in 3 blocks.
- Planning authority
- Dublin City Council
- Council reference
- 4362/23
- Council decision
- Refuse permission 18 Oct 2023
- Commission decision
- Refused 10 Sept 2024
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 24 Aug 2023Application received by the council
- 18 Oct 2023Council decision — Refuse permission
- 14 Nov 2023Appeal received by ACP
- 10 Sept 2024Appeal decidedJr window closed 5 Nov 2024
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |