An Coimisiún Pleanála · VA06F.319422 · Electricity Development Application
Strategic Infrastructure Development ABP-319422-24 · Commission category: SID (Not incl LAP SID cases)
Between the existing Woodland Substation, Batterstown, County Meath and the existing Belcamp Substation, Clonshaugh, Fingal, County Dublin, known as the ?East Meath ? North Dublin Grid Upgrade. https://www.eirgrideastmeathnorthdublin.ie/
Proposed development of a 400 kV underground: granted on appeal 5 Feb 2025.
Received by the Commission 28 Mar 2024We first saw it 11 Sept 2026, 15:23
Judicial review window closes 2 Apr 2025 closed 586 days ago
8 weeks from the Commission's decision (5 Feb 2025) · s.50 Planning and Development Act 2000
Case facts
Proposed development of a 400 kV underground cable
- Planning authority
- Fingal County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 5 Feb 2025
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 28 Mar 2024Appeal received by ACP
- 5 Feb 2025Appeal decidedJr window closed 2 Apr 2025
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 11 Sept 2026, 15:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 11 Sept 2026, 15:23 | open |