An Coimisiún Pleanála · PL06F.320701 · Planning Appeal
Park Road, Rush, Co. Dublin
Received by the Commission 29 Aug 2024We first saw it 11 Sept 2026, 15:23
Judicial review window closes 6 Jun 2025 closed 463 days ago
8 weeks from the Commission's decision (11 Apr 2025) · s.50 Planning and Development Act 2000
Case facts
Construction of 49 dwellings with all associated site works
- Planning authority
- Fingal County Council
- Council reference
- F24A/0066
- Council decision
- Grant permission 2 Aug 2024
- Commission decision
- Other 11 Apr 2025contribution_decided
- Inspector's recommendation
- development contribution scheme have been properly applied and I recommend that the Board directs the Council under subsection (13) (a) of Section…ATTACH Condition No 32 as follows. ABP 320701 - 24 Inspector’s Report Page
Timeline
- 1 Feb 2024Application received by the council
- 2 Aug 2024Council decision — Grant permission
- 29 Aug 2024Appeal received by ACP
- 11 Apr 2025Appeal decidedJr window closed 6 Jun 2025
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Matched passages full-text search
- development contribution scheme have been properly applied and I recommend that the Board directs the Council under subsection (13) (a) of Section…ATTACH Condition No 32 as follows. ABP 320701 - 24 Inspector’s Report Page
- requirement for two conditions relating to the same issue/levy. Therefore, I recommend that the Board omit condition No 20. Condition No 32 The appellant…original submission. Therefore, there is agreement by both ABP 320701 - 24 Inspector’s Report Page
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.