Lumcloon, Cloghan, County Offaly

Two independent power provider: granted on appeal 7 Jul 2025.

Received by the Commission 5 Mar 2025We first saw it 18 Sept 2026, 16:04
Judicial review window closes 1 Sept 2025 closed 443 days ago
8 weeks from the Commission's decision (7 Jul 2025) · s.50 Planning and Development Act 2000

Case facts

Construction of two independent power provider (IPP) buildings, associated infrastructure and all associated works. Access to the site is proposed through an upgraded existing entrance onto the R357 consented under planning reg. ref. 23/60111 nd through the existing Derrycarney substation entrance.

Planning authority
Offaly County Council
Council reference
—
Council decision
—
Commission decision
Granted with conditions 7 Jul 2025
Inspector's recommendation
No inspector's report published.

Timeline

  • 5 Mar 2025
    Appeal received by ACP
  • 7 Jul 2025
    Appeal decided
    Jr window closed 1 Sept 2025

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.018 Sept 2026, 16:04open