An Coimisiún Pleanála · 322069 · Appeal
Strategic Infrastructure Development ABP-322069-25 · Commission category: SID (Not incl LAP SID cases)
Located between the towns of Ballyragget and Castlecomer in North Kilkenny (www.ballynalackenwindfarmplanning.ie)
Proposed Development of the Ballynalacken: granted on appeal 15 Apr 2026.
Received by the Commission 13 Mar 2025We first saw it 18 Sept 2026, 16:04
Judicial review window closes 10 Jun 2026 closed 157 days ago
8 weeks from the Commission's decision (15 Apr 2026) · s.50 Planning and Development Act 2000
Case facts
Proposed Development of the Ballynalacken Windfarm Project
- Planning authority
- Kilkenny County Council
- Council reference
- —
- Council decision
- —
- Commission decision
- Granted with conditions 15 Apr 2026
- Inspector's recommendation
- No inspector's report published.
Timeline
- 13 Mar 2025Appeal received by ACP
- 15 Apr 2026Appeal decidedJr window closed 10 Jun 2026
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 18 Sept 2026, 16:04. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 18 Sept 2026, 16:04
| Source | Licence | Fetched | Link |
|---|---|---|---|