Mullafarry and Tawnaghmore Upper, Killala, Co. Mayo

Data centre: refused on appeal 15 Sept 2026.

Received by the Commission 21 May 2025We first saw it 16 Oct 2026, 23:03
Judicial review window closes 10 Nov 2026 8 days left
8 weeks from the Commission's decision (15 Sept 2026) · s.50 Planning and Development Act 2000

Case facts

Construction of a data centre and all associated site works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been submitted with the planning application.

Planning authority
Mayo County Council
Council reference
—
Council decision
—
Commission decision
Refused 15 Sept 2026
Inspector's recommendation
No inspector's report published.

Timeline

  • 21 May 2025
    Appeal received by ACP
  • 15 Sept 2026
    Appeal decided
    Jr window closes 10 Nov 2026

Documents

No documents listed on the case page yet.

    Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.

    Provenance

    Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 16 Oct 2026, 23:03. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.

    Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 16 Oct 2026, 23:03
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:03open