Refurbishment of dwelling and an extension with all associated site works
- Planning authority
- Fingal County Council
- Council reference
- F25A/0761E
- Council decision
- Refuse permission 9 Oct 2025
- Commission decision
- Refused 1 Oct 2026
- Inspector's recommendation
- No inspector's report published.
Timeline
- 19 Aug 2025Application received by the council
- 9 Oct 2025Council decision — Refuse permission
- 5 Nov 2025Appeal received by ACP
- 1 Oct 2026Appeal decidedJr window closes 26 Nov 2026
Documents
No documents listed on the case page yet.
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 16 Oct 2026, 23:03. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: An Coimisiún Pleanála cases (ArcGIS feed) · fetched 16 Oct 2026, 23:03
| Source | Licence | Fetched | Link |
|---|---|---|---|
| An Coimisiún Pleanála cases (ArcGIS feed) | CC BY 4.0 | 16 Oct 2026, 23:03 | open |