An Coimisiún Pleanála · PL29N.500595 · Planning Appeal
Block U, East Point Business Park, Alfie Byrne Road, Dublin 3
Received by the Commission 12 Jan 2026We first saw it 11 Sept 2026, 23:29
Applications only for this county. Appeals, zoning, RZLT and consultations: Dún Laoghaire-Rathdown and Fingal only for now.
Judicial review window closes 23 Jun 2026 closed 81 days ago
8 weeks from the Commission's decision (28 Apr 2026) · s.50 Planning and Development Act 2000
Case facts
Change of use of the Block U building from office use to medical use and all site development works.
- Planning authority
- Dublin City Council
- Council reference
- WEB5557/25
- Council decision
- Grant permission 18 Dec 2025
- Commission decision
- Granted 28 Apr 2026
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 31 Oct 2025Application received by the council
- 18 Dec 2025Council decision — Grant permission
- 12 Jan 2026Appeal received by ACP
- 28 Apr 2026Appeal decidedJr window closed 23 Jun 2026
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |