An Coimisiún Pleanála · PL06F.501133 · Planning Appeal
Orion Business Park, North-West Business Park, Ballycoolin, D15XE2N
Received by the Commission 9 Apr 2026We first saw it 11 Sept 2026, 15:23
Judicial review window closes 18 Sept 2026 6 days left
8 weeks from the Commission's decision (24 Jul 2026) · s.50 Planning and Development Act 2000
Case facts
Construction of a data centre building with all associated site works
- Planning authority
- Fingal County Council
- Council reference
- FW26A/0021E
- Council decision
- Grant permission 13 Mar 2026
- Commission decision
- Other 24 Jul 2026contribution_decided
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 20 Jan 2026Application received by the council
- 13 Mar 2026Council decision — Grant permission
- 9 Apr 2026Appeal received by ACP
- 24 Jul 2026Appeal decidedJr window closes 18 Sept 2026
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 15:23. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 15:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 15:23 | open |