Case facts
RETENTION: Change of use from workshop to a gym and all associated site works.
- Planning authority
- Dublin City Council
- Council reference
- WEB2990/25
- Council decision
- Grant retention permission 17 Apr 2026
- Commission decision
- pending
- Inspector's recommendation
- See the inspector's report (not yet indexed).
Timeline
- 29 Aug 2025Application received by the council
- 17 Apr 2026Council decision — Grant retention permission
- 11 May 2026Appeal received by ACP
Documents
Links go to pleanala.ie. We keep working copies for indexing only and do not serve them.
Provenance
Case row from the Commission's open-data feed (Cases 2016 onwards), fetched 11 Sept 2026, 23:29. Appeal counts on this site use the Commission's own case register, not NOAC or OPR totals.
Source: acp · fetched 11 Sept 2026, 23:29
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 11 Sept 2026, 23:29 | open |