PlanningRegister.ie
Carlow County Council · 18327

Kildavin Waste Water Treatment Plant, Kildavin, Co. Carlow

Approved in Nov 2018. The approval ran out in 2023.

  1. 13 Aug 2018Received
  2. 5 Oct 2018Conditional
  3. 7 Nov 2018Final approval
  4. 6 Nov 2023Approval ran out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 5 Oct 2018
Council
Carlow County Council
Type
PERMISSION
Site
126 m²

Live near Kildavin Waste Water Treatment Plant?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

to construct 1 No. 10.43 long x 5m wide and 1 No. 10.43m long x 7m wide sludge drying reed bed and associated site works within the boundary of the existing Kildavin Wastewater Treatment Plant

Planning details

Reference
18327
Local authority
Carlow County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
13 Aug 2018
Observations close
17 Sept 2018 (closed 2948 days ago)
Decision due
7 Oct 2018 · decided 5 Oct 2018
Decision
Conditional on 5 Oct 2018
Site area
126 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 8 · 500 m · 5 years

Explore this area on the map →

Zoning

N2.2 — Strategic infrastructure

Land tied to a national or strategic asset (airport, port, rail corridor). Uses are controlled by that asset's own plan.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 1
    Saint Paul's Church (Barragh)

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

18327 is a planning application to Carlow County Council for to construct 1 No. 10.43 long x 5m wide and 1 No. 10.43m long x 7m wide sludge drying, received on 13 Aug 2018; permission was granted with conditions on 5 Oct 2018.