Coppengh , Tullow , County Carlow

  1. 2 Aug 2023Received
  2. 6 Sept 2023Observations closed
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Withdrawn or invalid
Decision
Not yet
Council
Carlow County Council
Type
PERMISSION
Site
22.55 ha

What’s proposed

a five year planning permission for the development of the following elements: The erection and operation of a photovoltaic energy development which includes the erection of c. 20.9 ha fixed panels on ground mounted frames with an export capacity of c. twenty five mega-watt, 1no. energy storage compound with an export capacity of twenty five mega-watts, customer switchgear container, 1no. DSO substation which will be connected to the national grid, electrical transformer and inverter units on an overall site area of c. 22.45 ha, underground cabling and ducting, spare equipment container, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The proposed development will have a projected life span of 35 years

2360157 is a planning application to Carlow County Council for a five year planning permission for the development of the following elements: The, received on 2 Aug 2023; the file is recorded as incompleted application.

Planning details

Reference
2360157
Local authority
Carlow County Council
Status
Withdrawn or invalid · register status “INCOMPLETED APPLICATION
Received
2 Aug 2023
Observations close
6 Sept 2023 (closed 1108 days ago)
Decision due
No due date published
Decision
Not decided
Proposed development
a five year planning permission for the development of the following elements: The erection and operation of a photovoltaic energy development which includes the erection of c. 20.9 ha fixed panels on ground mounted frames with an export capacity of c. twenty five mega-watt, 1no. energy storage compound with an export capacity of twenty five mega-watts, customer switchgear container, 1no. DSO substation which will be connected to the national grid, electrical transformer and inverter units on an overall site area of c. 22.45 ha, underground cabling and ducting, spare equipment container, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The proposed development will have a projected life span of 35 years
As published by the register.
Site area
22.55 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Around this site this application first, then everything within 500 m

Explore from here
Click a dot to open its row.
Loading planning applications…
Free · during launch · limited time

Full planning report for 52.82039, -6.73683

Zoning, appeals, sold prices, flood and heritage — the whole area in one PDF.

No account, no payment. Not a statutory planning search.

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 171428). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/CarlowCC/AppFileRefDetails/2360157/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open