On lands including Straboe and, Killerrig, Carlow
Declared invalid.
- 11 Jun 2024Received
Planning details
- Status
- Withdrawn or invalid
- Reference
- 2460160
- Received
- 11 Jun 2024
- Site
- 132.30 ha
What’s proposed
The development will consist of permission for a Solar PV Energy Development with associated Battery Energy Storage System Compound with a total site area of c. 132.28ha, to include solar panels mounted on steel support structures, associated cabling and ducting, inverters, transformers, switchgear substations, auxiliary transformer, permanent storage containers, monitoring houses, composting toilet, BESS customer…
Show all
substation, battery blocks, BESS inverters and PCS (twin skid), BESS interface cabinets (BIC), backup generator, temporary construction compounds, tracks, boundary security fencing and security gates, CCTV, landscaping and ancillary works, with a 40year operational period. It is proposed that the Proposed Development will be accessed from four separate access points which will include (i) a new access created off the R726; (ii) a new entrance off Straboe Lane; (iii) a widened and improved existing entrance off Straboe lane; and (iv) use of an existing and previously consented entrance off the R418. A Natura Impact Statement (NIS) has been submitted to the Planning Authority…
Cut short by the council feed. Full text ↗
2 other applications within 500 m in five years
Open the reportNearby 2 · 500 m · 5 years
Protections nearby 250 m
- Recorded monument · 10
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2460160 is a planning application to Carlow County Council for the development will consist of permission for a Solar PV Energy Development with, received on 11 Jun 2024; the file is recorded as incompleted application.