Clare County Council · 18514
New Terminal Building, Shannon Airport, Shannon
Approved in Aug 2018.
- 25 Jun 2018Received
- 16 Aug 2018Conditional
- 16 Sept 2018Final approval
- 15 Sept 2023Approval runs out
- Status
- Approved
- Decision
- Conditional · 16 Aug 2018
- Council
- Clare County Council
- Type
- RETENTION
- Site
- 88 m²
Live near New Terminal Building?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
for alterations and refurbishment works which were carried out to the New Terminal Building
Planning details
- Reference
- 18514
- Local authority
- Clare County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 25 Jun 2018
- Observations close
- 30 Jul 2018 (closed 3004 days ago)
- Decision due
- 19 Aug 2018 · decided 16 Aug 2018
- Decision
- Conditional on 16 Aug 2018
- Site area
- 88 m² from the mapped boundary, not the council's figure
Nearby 10 · 500 m · 5 years
- GrantedShannon Airport , Shannon , Co. Clare
- GrantedEir Exchange , Shannon Airport , Shannon Co. Clare
- GrantedShannon Airport , Rineanna South , Shannon Co. Clare
- GrantedShannon Airport , Shannon , Co. Clare
- GrantedShannon Airport , Rineanna South , Shannon Co. Clare
- GrantedShannon Airport , Rineanna South , Shannon Co . Clare
- GrantedShannon Airport , Rineanna South , Shannon
- GrantedShannon Airport , Shannon , Co. Clare
Show all 10
Zoning
N1.3 — Airport
Tied to the efficient operation and development of the airport under its own plan — which also means aircraft noise contours apply.
Protections nearby 250 m
- NIAH-recorded building · 1
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
18514 is a planning application to Clare County Council for for alterations and refurbishment works which were carried out to the New Terminal, received on 25 Jun 2018; permission was granted with conditions on 16 Aug 2018.