Clare County Council · 22345
Ballyscanlan, Crusheen, Co Clare
Approved in Jul 2022. Building started in 2023.
- 14 Apr 2022Received
- 7 Jun 2022Conditional
- 14 Jul 2022Final approval
- 31 Jan 2023Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 7 Jun 2022
- Reference
- 22345
- Received
- 14 Apr 2022
- Units
- 1
- Site
- 6,016 m²
What’s proposed
The development will consist of - Construction of a new dwelling & garage, new access, installation of a wastewater treatment system, percolation area & all associated site works
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Distance
Time
Building started
- 31 Jan 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0096915CE
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
22345 is a planning application to Clare County Council for the development will consist of - Construction of a new dwelling & garage, new access, received on 14 Apr 2022; permission was granted with conditions on 7 Jun 2022.