Corebeg, Doora, Ennis Co Clare
Approved in Jan 2023. Building started in 2023, signed off as finished in Sep 2025.
- 13 Oct 2022Received
- 2 Dec 2022Conditional
- 18 Jan 2023Final approval
- 11 Sept 2023Building started
- 2 Sept 2025Signed off
Planning details
- Status
- Building started
- Decision
- Conditional · 2 Dec 2022
- Reference
- 22929
- Received
- 13 Oct 2022
- Units
- 1
- Site
- 2,920 m²
What’s proposed
To construct a new dwelling house with private garage, site entrance, on-site wastewater treatment system and all other associated site works
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Homes nearby
Building started
- 11 Sept 2023 · Builder told the council work was starting CN0104627CE
Zoning
Zoned to protect the open land between urban areas. Development is strongly resisted.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Protections nearby 250 m
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
22929 is a planning application to Clare County Council for to construct a new dwelling house with private garage, site entrance, on-site wastewater, received on 13 Oct 2022; permission was granted with conditions on 2 Dec 2022.