Teergonean, Doolin, Co Clare

Approved in 2025. Building started in 2025.

  1. 2 May 2025Received
  2. 25 Jun 2025Conditional
  3. 29 Jul 2025Final approval
  4. 30 Aug 2025Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building startedi
Decision
Conditional · 25 Jun 2025
Council
Clare County Council
Type
PERMISSION
Units
1
Site
1,732 m²

Live near Teergonean?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

to construct a new dwelling, install a waste water treatment system & all other associated site and ancillary works

Planning details

Reference
25143
Local authority
Clare County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
2 May 2025
Observations close
6 Jun 2025 (closed 486 days ago)
Decision due
26 Jun 2025 · decided 25 Jun 2025
Decision
Conditional on 25 Jun 2025
Proposed development
to construct a new dwelling, install a waste water treatment system & all other associated site and ancillary works
As published by the register.
Site area
1,732 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 23 · 500 m · 5 years

Show all 23

Explore this area on the map →

Homes nearby

Building started

  • 30 Aug 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0132787CE

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 1
    R126179

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

25143 is a planning application to Clare County Council for to construct a new dwelling, install a waste water treatment system & all other, received on 2 May 2025; permission was granted with conditions on 25 Jun 2025.