PlanningRegister.ie
Clare County Council · 2548

Corbally, Quin, Co Clare

Approved in May 2025. Building started in 2025.

  1. 24 Feb 2025Received
  2. 16 Apr 2025Conditional
  3. 22 May 2025Final approval
  4. 21 Oct 2025Building started

Earlier approval here ran out with no sign of building: 22226 (2022)

Planning details

Status
Building startedi
Decision
Conditional · 16 Apr 2025
Reference
2548
Type
PERMISSION CONSEQUENT
Received
24 Feb 2025
Units
1
Site
2,913 m²

What’s proposed

Permission consequent on the grant of outline permission (Reference No. P22/226) to construct a dwelling house, garage, a proprietary waste water treatment system and ancillary site works

4 other applications within 500 m in five years

Open the report

Nearby 4 · 500 m · 5 years

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 28 Oct 2025 · Builder told the council small works were starting CN0134723CE
  • 21 Oct 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0134663CE
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2548 is a planning application to Clare County Council for permission consequent on the grant of outline permission (Reference No. P22/226) to, received on 24 Feb 2025; permission was granted with conditions on 16 Apr 2025.