PlanningRegister.ie
Clare County Council · 2560682

Creggane, Quilty, Co. Clare V95 X7X9

Approved in Jan 2026. Building started in 2026.

  1. 7 Nov 2025Received
  2. 15 Dec 2025Conditional
  3. 27 Jan 2026Final approval
  4. 3 Apr 2026Building started
Status
Building startedi
Decision
Conditional · 15 Dec 2025
Council
Clare County Council
Type
PERMISSION
Units
1
Site
1,870 m²

What’s proposed

for demolition of part of the existing dwelling in the south, demolition of the existing shed, alterations and modifications to the inside of the existing dwelling, construction of an extension to the south-west part of the existing dwelling, construction of a detached garage, alterations to the existing site boundaries to include site access and construction of boundary walls and installation of metal access gates, connection to Clare County Council wastewater sewer mains, and all associated site works

Planning details

Reference
2560682
Local authority
Clare County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
7 Nov 2025
Observations close
12 Dec 2025 (closed 331 days ago)
Decision due
10 Jan 2026 · decided 15 Dec 2025
Decision
Conditional on 15 Dec 2025
Site area
1,870 m² from the mapped boundary, not the council's figure

Live near Creggane?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 3 Apr 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0139911CE

Protections nearby 250 m

  • Recorded monument · 1
    R119845

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2560682 is a planning application to Clare County Council for for demolition of part of the existing dwelling in the south, demolition of the existing, received on 7 Nov 2025; permission was granted with conditions on 15 Dec 2025.