Approved in Sept 2023. Building started in 2024.

  1. 22 Jun 2023Received
  2. 16 Aug 2023Conditional
  3. 26 Sept 2023Final approval
  4. 19 Jun 2024Building started

Planning details

Status
Building startedi
Decision
Conditional · 16 Aug 2023
Reference
2342103
Received
22 Jun 2023
Site
1,798 m²

What’s proposed

Permission is sought for alterations to the external wall finishes, removal of masonry chimney stacks, modifications to front elevation lower roof, relocation of 1st floor rear window and construct new window, construction of a single storey side extension and all associated site works to an existing dwellinghouse

1 other application within 500 m in the last year · 1 open for comments

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 19 Jun 2024 · Builder told the council small works were starting CN0116599CY

Zoning

P5 — Rural and agricultural

Land zoned to stay rural. New houses are restricted to demonstrated local need under the rural-housing policy of the development plan.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2342103 is a planning application to Cork City Council for permission is sought for alterations to the external wall finishes, removal of masonry, received on 22 Jun 2023; permission was granted with conditions on 16 Aug 2023.