What’s proposed

Permission for an underground grid connection at this site within the townlands of Carhoo, Kilcully and Kilbarry, Cork City. The development will consist of: A 10-year permission for the installation of an underground grid connection within an overall site area of 2.81 hectares.

Show all

The underground grid connection is to be installed within the L2951 and L2963 public roads, this includes the installation of 3 no. underground medium voltage electrical cables, 1 no. fibre communications cable, 2 no. joint bays and associated infrastructure to allow communications between the proposed 38kV on-site substation and the Kilbarry 110kV substation, Blackpool, Cork City. The total length of the cable is c. 4,449m., of which c. 2,428m. within the jurisdiction of Cork City Council and c. 2021m. will be within the jurisdiction of Cork County Council. A concurrent planning application will be lodged with Cork County Council for the remainder of the underground cable within public roads and associated solar farm including proposed 38kV substation to allow connection to the proposed 38kV substation in the townland of Rahanisky, County Cork under Section 34 of the Planning and Development Act 2000 (PDA) (as amended)

  1. 21 Jul 2023Received
  2. 20 May 2024Conditional
  3. 1 Jul 2024Final approval
  4. 1 Jul 2034Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 20 May 2024
Reference
2342173
Received
21 Jul 2023
Site
2.89 ha

2 other applications within 500 m in the last year

Get the full report

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Zoning

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

G1 — Open space with recreation

Open space with active recreational amenities — pitches, courts, play areas.

G3 — High amenity

Protected high-amenity landscape. Development is resisted to preserve the character of the area.

P5 — Rural and agricultural

Land zoned to stay rural. New houses are restricted to demonstrated local need under the rural-housing policy of the development plan.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • NIAH-recorded building · 1
    Glennamought Bridge
  • Recorded monument · 8
    Ringfort - rath; Standing stone
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2342173 is a planning application to Cork City Council for permission for an underground grid connection at this site within the townlands of, received on 21 Jul 2023; permission was granted with conditions on 20 May 2024.