PlanningRegister.ie
Cork City Council · 2443306

The Maltings , South Link , Togher

  1. 7 Oct 2024Received
  2. 17 Feb 2025Conditional
  3. 1 Apr 2025Final grant
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional · 17 Feb 2025
Council
Cork City Council
Type
PERMISSION
Site
1.19 ha

What’s proposed

Permission for the construction of reduced emissions malting infrastructure as part of the decarbonisation road map for the business. The development will consist of the construction of a four storey energy building with roof mounted equipment, single storey utilities building, a kiln with roof mounted ancillary equipment, a germination vessel with roof mounted ancillary equipment and adjoining three storey aeration building, associated malt conveying system including a six storey elevator enclosure, demolition of existing single storey storage building and all associated site works including, connections to existing on site services, surface water management, concrete paving and all ancillary site works as part of the malting plant development project at their site at the Maltings, South Link, Togher, Co Cork. A Natura Impact Statement (NIS) will be submitted to the planning authority with the application

2443306 is a planning application to Cork City Council for permission for the construction of reduced emissions malting infrastructure as part of, received on 7 Oct 2024; permission was granted with conditions on 17 Feb 2025.

Planning details

Reference
2443306
Local authority
Cork City Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
7 Oct 2024
Observations close
11 Nov 2024 (closed 687 days ago)
Decision due
17 Feb 2025 · decided 17 Feb 2025
Decision
Conditional on 17 Feb 2025
Proposed development
Permission for the construction of reduced emissions malting infrastructure as part of the decarbonisation road map for the business. The development will consist of the construction of a four storey energy building with roof mounted equipment, single storey utilities building, a kiln with roof mounted ancillary equipment, a germination vessel with roof mounted ancillary equipment and adjoining three storey aeration building, associated malt conveying system including a six storey elevator enclosure, demolition of existing single storey storage building and all associated site works including, connections to existing on site services, surface water management, concrete paving and all ancillary site works as part of the malting plant development project at their site at the Maltings, South Link, Togher, Co Cork. A Natura Impact Statement (NIS) will be submitted to the planning authority with the application
As published by the register.
Site area
1.19 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 12 applications within 500 m in the last 5 years

Show all 12

Explore this area on the map →

Homes nearby

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    C2.1 — Economic development and employment

    Light Industry and Related Uses: To provide for light industry and related uses.

    Zoned for employment uses. Housing is not the intended use here.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 196669). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://planning.corkcity.ie/AppFileRefDetails/2443306/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open