Approved in Apr 2025. Built and signed off.

  1. 17 Dec 2024Received
  2. 18 Feb 2025Conditional
  3. 1 Apr 2025Final approval
  4. 29 Aug 2025Building started
  5. 8 Dec 2025Signed off

Planning details

Status
Building started
Decision
Conditional · 18 Feb 2025
Reference
2443508
Received
17 Dec 2024
Site
904 m²

What’s proposed

Permission for the following: to construct new retail Mezz floor 536m2, with staff areas, escape corridor & staircase, internal lift and circulation stairs, rear escape and roller shutter doors, provision of external aircon units to rear, and replacement signage. All associated and ancillary works necessary to facilitate the development

6 other applications within 500 m in the last year

Open the free report

Nearby 6 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 29 Aug 2025 · Builder told the council work was starting CN0132615CY

Zoning

C1.2 — Retail warehousing

Zoned for bulky-goods retail warehousing — large sheds, large car parks.

Protections nearby 250 m

  • Recorded monument · 1
    Excavation - miscellaneous
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2443508 is a planning application to Cork City Council for permission for the following: to construct new retail Mezz floor 536m2, with staff, received on 17 Dec 2024; permission was granted with conditions on 18 Feb 2025.