Tullagreen Carrigtwohill
- 17 Feb 2006Received
- 12 Apr 2006Conditional
- 18 May 2006Final grant
- Status
- Granted with conditions
- Decision
- Conditional · 12 Apr 2006
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 15.53 ha
What’s proposed
Construction of a two storey manufacturing building, a single storey mix room extension (7.8m high) to the Hi-flow building, a thermal oxidiser, stack (14.6m high)and its associated base, cooling tower and plinth (5m high), solvent recovery unit (15m) and plinth, Drum store, an additional 100 no. carpark spaces, an extension to the existing piperack, associated site works and ancillary landscaping, the relocation of the proposed extension to existing tank farm and tank farm electrical room (MCC) previously granted under P.A. ref: S/01/5172 (change of plan), the construction of a two storey maintenance workshop as granted under P.A. ref: S/01/5172, also the retention of a small single storey water services room as an extension to the West of the Hi-flow building
06/4900 is a planning application to Cork County Council for construction of a two storey manufacturing building, a single storey mix room extension, received on 17 Feb 2006; permission was granted with conditions on 12 Apr 2006.
Planning details
- Reference
- 06/4900
- Local authority
- Cork County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 17 Feb 2006
- Observations close
- 24 Mar 2006 (closed 7483 days ago)
- Decision due
- 13 Apr 2006 · decided 12 Apr 2006
- Decision
- Conditional on 12 Apr 2006
- Proposed development
- Construction of a two storey manufacturing building, a single storey mix room extension (7.8m high) to the Hi-flow building, a thermal oxidiser, stack (14.6m high)and its associated base, cooling tower and plinth (5m high), solvent recovery unit (15m) and plinth, Drum store, an additional 100 no. carpark spaces, an extension to the existing piperack, associated site works and ancillary landscaping, the relocation of the proposed extension to existing tank farm and tank farm electrical room (MCC) previously granted under P.A. ref: S/01/5172 (change of plan), the construction of a two storey maintenance workshop as granted under P.A. ref: S/01/5172, also the retention of a small single storey water services room as an extension to the West of the Hi-flow buildingAs published by the register.
- Site area
- 15.53 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Full planning report for 51.90456, -8.27764
Zoning, appeals, sold prices, flood and heritage — the whole area in one PDF.
No account, no payment. Not a statutory planning search.
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 322582). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=06/4900.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |