PlanningRegister.ie
Cork County Council · 14/4985

Glanycummane Upper Freemount Charleville Co. Cork

Approved in Sept 2014. The approval ran out in 2019.

  1. 14 May 2014Received
  2. 18 Aug 2014Conditional
  3. 23 Sept 2014Final approval
  4. 23 Sept 2019Approval ran out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 18 Aug 2014
Council
Cork County Council
Type
PERMISSION
Site
3,424 m²

Live near Glanycummane Upper Freemount…?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Construction of a dwelling house with packaged wastewater treatment system and polishing filter, domestic garage, domestic well and all associated site works

Planning details

Reference
14/4985
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
14 May 2014
Observations close
18 Jun 2014 (closed 4499 days ago)
Decision due
4 Sept 2014 · decided 18 Aug 2014
Decision
Conditional on 18 Aug 2014
Proposed development
Construction of a dwelling house with packaged wastewater treatment system and polishing filter, domestic garage, domestic well and all associated site works
As published by the register.
Site area
3,424 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 3 · 500 m · 5 years

Explore this area on the map →

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 8
    Fulacht fia

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

14/4985 is a planning application to Cork County Council for construction of a dwelling house with packaged wastewater treatment system and polishing, received on 14 May 2014; permission was granted with conditions on 18 Aug 2014.