Cork County Council · 16/6260
Garraun North Donoughmore Co. Cork
Approved in Feb 2017. The approval ran out in 2022.
- 9 Sept 2016Received
- 19 Jan 2017Conditional
- 27 Feb 2017Final approval
- 27 Feb 2022Approval ran out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Approved
- Decision
- Conditional · 19 Jan 2017
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 3,220 m²
Live near Garraun North Donoughmore Co. Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
The construction of a detached dwelling, potable well, bio filtration treatment unit, entrance, garage and store area and all associated site works
Planning details
- Reference
- 16/6260
- Local authority
- Cork County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 9 Sept 2016
- Observations close
- 14 Oct 2016 (closed 3649 days ago)
- Decision due
- 26 Jan 2017 · decided 19 Jan 2017
- Decision
- Conditional on 19 Jan 2017
- Proposed development
- The construction of a detached dwelling, potable well, bio filtration treatment unit, entrance, garage and store area and all associated site worksAs published by the register.
- Site area
- 3,220 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 2 · 500 m · 5 years
Homes nearby
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 3
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
16/6260 is a planning application to Cork County Council for the construction of a detached dwelling, potable well, bio filtration treatment unit, received on 9 Sept 2016; permission was granted with conditions on 19 Jan 2017.