PlanningRegister.ie
Cork County Council · 18/4345

Brinny Innishannon Co. Cork

Approved in Mar 2018. Building started.

  1. 9 Feb 2018Received
  2. 29 Mar 2018Conditional
  3. 15 May 2018Final approval
  4. 22 Feb 2019Building started
Status
Building started
Decision
Conditional · 29 Mar 2018
Council
Cork County Council
Type
RETENTION
Site
3,023 m²

Live near Brinny Innishannon Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Retention for the construction of a 14sqm first floor extension to the east façade of an existing production building (Building 8) for a new cold room storage for industrial/pharmaceutical use and the construction of 2no. new door openings to the ground floor of the north façade of an existing production building (Building 22). This application relates to a development which comprises an activity for which an Industrial Emissions Licence under part IV of the Environment Protection Agency 1992 (as amended) is required

Planning details

Reference
18/4345
Local authority
Cork County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
9 Feb 2018
Observations close
16 Mar 2018 (closed 3140 days ago)
Decision due
5 Apr 2018 · decided 29 Mar 2018
Decision
Conditional on 29 Mar 2018
Site area
3,023 m² from the mapped boundary, not the council's figure

Nearby 7 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Building started

  • 22 Feb 2019 · Builder told the council work was starting (opted out of the finish sign-off) CN0048531CC

Protections nearby 250 m

  • NIAH-recorded building · 2
    post box; Brinny Church of Ireland Church
  • Recorded monument · 6
    Mill - corn; Inscribed stone

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

18/4345 is a planning application to Cork County Council for retention for the construction of a 14sqm first floor extension to the east façade of an, received on 9 Feb 2018; permission was granted with conditions on 29 Mar 2018.