Kilberrihert Coachford Co. Cork
Approved in 2018. Approval ran out in 2023.
- 16 May 2018Received
- 9 Oct 2018Conditional
- 16 Nov 2018Final approval
- 16 Nov 2023Approval ran out
- Status
- Approved
- Decision
- Conditional · 9 Oct 2018
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 2,299 m²
Live near Kilberrihert Coachford Co. Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
An extension to the existing electricity substation, comprising of the construction of up to 4 no. battery storage units, palisade fencing, bunded concrete plinths, associated electrical equipment, transformers and all ancillary site works
Planning details
- Reference
- 18/5240
- Local authority
- Cork County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 16 May 2018
- Observations close
- 20 Jun 2018 (closed 3031 days ago)
- Decision due
- 11 Oct 2018 · decided 9 Oct 2018
- Decision
- Conditional on 9 Oct 2018
- Proposed development
- An extension to the existing electricity substation, comprising of the construction of up to 4 no. battery storage units, palisade fencing, bunded concrete plinths, associated electrical equipment, transformers and all ancillary site worksAs published by the register.
- Site area
- 2,299 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
18/5240 is a planning application to Cork County Council for an extension to the existing electricity substation, comprising of the construction of, received on 16 May 2018; permission was granted with conditions on 9 Oct 2018.